Current Status: Storm damage repairs were designed, permitted, and bid in 2024. Contractors mobilized on December 2, 2024 to begin erecting scaffolding around the impacted tower. Demolition and reconstruction is anticipated to run through late 2025.

Upcoming: Steel installation to support the replacement walls was completed in March, framing was completed in April, fireproofing installed in May, and installation of sheathing is currently underway with the exterior finish expected to begin installation in June.

Schedule updates and progress photos of the work will be posted to this page as the project advances.