Details for Phase 2 of the Carter Park ADA Improvements impacting the multipurpose field and associated restrooms, concessions, & parking as well as the adjacent little-league baseball field and greenway section
Phase 2 of the Carter Park ADA Improvements provides for four fully-compliant ADA parking spaces in the front parking lot, corrects ADA deficiencies at the adjacent restroom and concessions, and provides an accessible path to and seating for both the multipurpose and little league fields.
This phase of the project will also begin construction of a new, fully-accessible playground for the park. The new location enhances visibility of the playground and provides space for a larger playground. This phase of the project only installs the drainage and foundations required for the playground. Playground equipment is anticipated to be installed during Phase 3 with playground surfacing being completed during Phase 4.