Overall
Nine of the 25 sites assessed in the city’s 2015 ADA Assessment have active projects. This page summarizes the status for these active projects. Projects are listed in alphabetical order by site. Detailed information for projects currently under construction can be found on the project pages linked above.

Holston River Park
Initial designs have been completed to the Design Development stage. The design will be advanced to its final stage once funding for construction is allocated.

Inskip Pool and Park
Assessment, design, and permitting have been completed. This project is currently on hold pending funding allocation.

Inskip Recreation Center — Details Here
COMPLETE — Design was completed mid-2019 permits obtained in late-2019. Construction began in February and was completed in early June. See the Inskip Recreation page for more details and photos of the completed project..

John. T. O’Connor Senior Center — Details Here
COMPLETE — Design was completed in late 2018 and permits approved in December. A construction contract was awarded to Shelton General Contractors with work beginning in January 2019 and completed a year later. See the O’Connor Center page for more details.

Lonsdale Recreation Center
This site is part of a property exchange with the county. As such the ADA improvements for this site have been cancelled.

Sam Duff Park
Assessment and design have been completed. Permitting is anticipated to begin in October with a target of advancing this project to the construction phase in early 2021.

Sharp’s Ridge Veteran’s Memorial Park — Details Here
COMPLETE — Design was completed in late 2018 and permits approved in December. A construction contract was awarded to Wright General Contracting with work beginning in January 2019 and substantially complete by mid-summer. See the Sharp’s Ridge page for more details.

Victor Ashe Park
Initial designs have been completed to the Design Development stage. The design will be advanced to its final stage once funding for construction is allocated.

West Hills/John Bynon Park
Initial designs have been completed to the Design Development stage. The design will be advanced to its final stage once funding for construction is allocated.