Project Complete

Construction is underway by Blalock Construction. Crews installed erosion control last fall and then removed trees and vegetation from the site towards the end of the year. Nonstop rain in January and February left the site too wet to work, but some dryer spells in March have allowed for significant progress including completing a cut through a hill on UT’s property that was the largest grading operation on the project. Crews are now preparing for the installation of the new box culvert across the intermittent stream on the UT Farm property. The culvert should be installed in the next month if weather holds.

You can see photos of some of the project progress below.