The list below summarizes changes to the original construction documents.

  1. Walls
    • Walls for several offices (P114, M101, and M110) have been adjusted slightly to avoid conflicts with existing floor outlets.
    • The small wall and door separating rooms P107 and P118 have been eliminated due to conflicts (also 2A).
  2. Doors
    • The small wall and door separating rooms P107 and P118 have been eliminated due to conflicts (also 1B).
    • The door to the north (downtown side) corridor from P115 has been eliminated (drafting error).
  3. Flooring
    The building standard carpet has been substituted for much of the luxury vinyl plank (LVP) in the lobby areas to resolve a conflict between the LVP and the building's electrical floor chases.